*Project 98% complete in four months |
• Clear 47 acres • Install 12,000lf erosion
control • Strip & remove 65,000cy of top soil • 310,000 yards
cuts & fills • 90,000cy blasting • 100,000cy processed materials
produced • 60,000sy asphalt • 38,000sf retaining wall • 5,600lf
sewer • 55 drainage structures • 7,000lf of drainage • Installed
two detention ponds • 10,000lf water • 15,500lf curbing • 2,500ft
of irrigation sleeve • 4,000lf underground conduit • 4,000ft
of gas main extension • Excavate, backfill and prep BJ’s Building
pad • Install pump house |